Kitchen extract removes heat and contaminants, but replacement air must also be designed. Poor balance can make doors difficult to open, pull odours into dining areas or reduce hood performance. The solution depends on cooking duty, hood selection, building systems and approved routes.

Quick answer

Have the kitchen consultant and qualified mechanical engineer design extract and replacement air together using confirmed equipment and building data. Coordinate distribution, controls, access, noise and commissioning before ceiling closure.

Freeze the cooking schedule

List appliances, fuel or power, duty, operating periods and selected hood systems. Changes to the cooking line can alter extract and replacement-air requirements. Keep the kitchen schedule revision-controlled.

Do not estimate air quantities from restaurant seats or a visual reference. The responsible specialists must calculate them.

Understand the base building

Obtain landlord information for available shafts, fresh-air systems, discharge points, plant locations and operating restrictions. Survey actual conditions and confirm approval responsibilities before pricing.

Where existing infrastructure is reused, assess capacity and condition instead of assuming connection permission.

Coordinate air distribution

Place supply air so it supports hood capture and staff comfort without creating disruptive drafts. Coordinate diffusers with ceilings, lights, sprinklers and equipment. Review dining and kitchen pressure relationships with the engineer.

Link the solution to the wider restaurant kitchen MEP guide.

Protect access and acoustics

Show filters, fans, dampers, controls and cleaning or maintenance access. Avoid enclosing equipment behind fixed decorative ceilings. Assess noise and vibration at neighbouring spaces and external discharge locations.

Define who provides supports, power, controls, fire interfaces and builder’s work in the responsibility matrix.

Commission under representative duty

Test air systems, controls and relevant safety interfaces under the approved method. Verify operation with the cooking equipment and building systems in their intended modes. Record readings, settings and outstanding actions.

Dubai Municipality and landlord requirements should be confirmed for the specific establishment; this guide does not set technical values.

Dubai project note: Building management rules, landlord requirements and authority pathways vary by location and project scope. Confirm the applicable approvals before finalising drawings, programme or cost.

Frequently asked questions

Is make-up air the same as comfort air-conditioning?

Not necessarily. The mechanical engineer should define each air system and how they interact for the actual kitchen and building.

Can an existing extract connection always be reused?

No. Capacity, condition, route, approvals and the proposed cooking duty must be verified before reliance.

References and scope

References checked on 19 October 2026. Confirm current requirements and product instructions for the actual project; these links do not constitute project approval.