Restaurant interior and commercial kitchen planning project in Dubai

Restaurant MEP planning begins with the menu, equipment schedule and operating workflow.

A restaurant kitchen is a production system. The menu determines equipment, heat, power, gas, water, drainage, extraction, cold storage and waste. If the concept layout is approved before these requirements are understood, later coordination can reduce seating, change ceilings or create expensive service upgrades.

Quick answer

Freeze the menu and production method, obtain confirmed equipment data, map food and staff flows, calculate service loads, coordinate extraction with make-up air, resolve drainage and grease management, integrate fire safety, and preserve safe maintenance access.

Turn the menu into an equipment schedule

List every appliance, its size, duty, heat output, power or gas connection, water, drainage and ventilation needs. Include preparation, washing, refrigeration, holding and specialist equipment rather than focusing only on the cooking line.

Plan clean operational flow

Map receiving, storage, preparation, cooking, pass, dish return, washing and waste. Reduce cross-traffic and give staff safe working clearances. Coordinate door swings, trolleys and delivery routes with the final equipment, not generic symbols.

Balance extraction and make-up air

Kitchen extraction must work with replacement air and the wider air-conditioning strategy. Poor balance can create heat, odours, door pressure and uncomfortable dining areas. Confirm routes, discharge constraints, access and noise control early.

Coordinate power, gas, water and drainage

Verify incoming capacity and diversity assumptions. Set floor drains, grease management, hot water, isolation points and cleaning access before screed and waterproofing. Equipment changes after first fix often affect several systems at once.

Design for fire safety and maintenance

Coordinate suppression, detection, emergency isolation, safe finishes and access with qualified specialists and the applicable approval pathway. Filters, fans, drains and equipment must remain accessible for cleaning, testing and replacement after opening.

Dubai project note: Building management rules, landlord requirements and authority pathways vary by location and project scope. Confirm the applicable approvals before finalising drawings, programme or cost.

Frequently asked questions

When should kitchen equipment be selected?

Core equipment and verified service data should be available before detailed MEP coordination and authority submissions.

Can the kitchen layout change during construction?

Minor adjustments may be possible, but late changes can affect extraction, drainage, power, fire systems, waterproofing and the opening programme.

Why is make-up air important?

Extraction removes large volumes of air. Coordinated replacement air helps maintain comfort, capture performance and reasonable pressure relationships.